A network-related or instance-specific error occurred while establishing a connection to SQL Server. The server was not found or was not accessible. Verify that the instance name is correct and that SQL Server is configured to allow remote connections. (provider: Named Pipes Provider, error: 40 - Could not open a connection to SQL Server) India's 200 Miles-Per-Hour Bullet Train Has Starting Trouble, National : Today Indya

Latest News

  • Home
  • India's 200 Miles-Per-Hour Bullet Train Has Starting Trouble
India's 200 Miles-Per-Hour Bullet Train Has Starting Trouble
Monday, October 22, 2018 IST
India

The planned 316-mile line links the financial capital of Mumbai with the economic hub of Ahmedabad

 
 

India's bullet train project is moving at the pace of a commuter train instead.
 
A year after the project was kicked off, only 0.9 hectares of land have been acquired out of the 1,400 hectares needed, according to the government company leading the project. The $15 billion facility, the highlight of Prime Minister Narendra Modi's drive to upgrade infrastructure, is facing resistance from farmers unhappy with the compensation for land taken away from them.
 
The planned 316-mile line linking the financial capital of Mumbai with the economic hub of Ahmedabad -- roughly the distance between Los Angeles and San Francisco -- was meant to be a big leap from the trains of Indian Railways, Asia's oldest network with over 165 years of history. At the current rate of land acquisition, the bullet train built with Japan's 'Shinkansen' technology risks missing its 2023 completion target.
 
"Land acquisition is a very common problem in India and many projects are delayed, there's no question about that," said Raghbendra Jha, an economics professor at the Australian National University. "I've seen many instances like this."
 
The protests highlight the challenge PM Modi faces in implementing his flagship projects across railways, ports and airports to cement India's position as world's fastest growing economy. Projects worth Rs. 754 billion ($10.2 billion) were completed in the quarter ended September 2018, less than half of the targeted 2 trillion rupees, according to the Centre for Monitoring Indian Economy.
 
"The project is very high-level and highly visible, publicity-wise," said Nilanjan Mukhopadhyay, a political analyst and author of a biography on PM Modi. "If people are beginning to protest, this is going to undermine Mr. Modi's image as someone who can implement things very seamlessly."
 
For Japanese suppliers to the bullet train such as East Japan Railway Co., Hitachi Ltd. and Kawasaki Heavy Industries Ltd., the project was a big victory over China's CRRC Corp., Siemens AG and Bombardier Inc. After years of international marketing, India became a rare buyer for the Shinkansen.
 
A group of farmers affected by the project have petitioned the Gujarat High Court, which has sought the government's stand on the plea on Nov. 22, according to court documents. The farmers have also questioned the government's power to acquire farm land for public-private partnership projects, documents show.
 
The courts had earlier refused to put the land acquisition process on hold.
 
 

 
 

The National High Speed Rail Corporation, which is building the project, said there are no funding gaps despite the delay in land acquisition. The date of operation for the project will be in August 2022, said Dhananjay Kumar, a spokesman for the company, a year before its official completion target. The company is "committed to take care of the interests of the affected farmers," he said.
 
Farmer protests have stalled projects in the past. A decade back, Tata Motors Ltd. had to delay selling the world's cheapest car, the Nano, after violent protest by farmers forced the owner of Jaguar Land Rover to abandon a factory in the state of West Bengal and instead choose a new site in western Gujarat. Land acquisition has also been an issue in the potential construction of an oil refinery with Saudi Aramco in Maharashtra.
 
India isn't the only country where a planned bullet train has struggled to take off because of land acquisition problems.
 
A $6 billion high-speed rail project connecting Jakarta and Bandung is entangled in Indonesia's infamous red tape and difficulties in acquiring land for the project. While construction was meant to begin in August 2016, only 7.6 percent of the work has been done on the 142-kilometer railway line at the end of August, according to the Jakarta Post.
 
For Shailesh Kumar, director for Asia at political risk consultancy Eurasia Group, land acquisition is "an eternal story" in India. "But I have a suspicion that once the bullet train is there, and users accept it, you'll see massive expansion," he said.
 
Project Highlights:
 
The official target for completion is 2023. Government says it will attempt to have it running a year earlier Total estimated cost is 1.08 trillion rupees While the train is designed to run at 350 kilometers per hour, it will operate at a maximum speed of 320 kilometers (200 miles per hour), cutting down travel time between the two cities to about two hours from about seven hours. Most of the corridor will be elevated, but will include a 21-kilometer tunnel with seven kilometers under the Arabian Sea. 

 
 
 
 
 

Related Topics

 
 
 

Trending News & Articles

 Article
Here is the full list of 827 porn websites banned by the DoT

While the Uttarakhand High Court has asked to block 857 websites, the Ministry of Electronics and IT (Meity) found 30 portals without any pornographic content. ...

Recently posted . 64K views . 1 min read
 

 Article
Class XII Boys Raped 16-Year-old in Dehradun School After Watching Porn on Phone: Police

The four boys as well as five school officials, including the director and principal, were arrested after the incident. The minors were presented before the Juvenil...

Recently posted . 10K views . 1 min read
 

 Article
Sept 27,2001 Rahul Gandhi and his girl friend Veronique,was arrested in Logan airport in Boston

Rahul was having an Italian passport and was carrying suitcase full of dollars. Some say it was about was it $2 million. Rahul and his girl friend was th...

Recently posted . 9K views . 7 min read
 

 Article
TOP 10 GYM EQUIPMENT BRANDS IN INDIA 2017

True – Tr...

Recently posted . 8K views . 83 min read
 

 
 

More in

 Article
Indian Railways Guntakal station becomes first to install ‘Ulta Chaata’ for rainwater harvesting!

As many as six such 'Ulta Chaatas' which are canopies shaped like inverted umbrellas with solar panels fitted on top, have been installed at the Guntakal ra...

Recently posted. 1K views . 1 min read
 

 Article
IIT-Delhi boys launch roll on for period pain relief on Women’s Day

Also called as women empowerment entrepreneurs, Archit Agarwal (20) and Harry Sehrawat (19), launched 'Sanfe stand and pee' product last year to save wome...

Recently posted. 928 views . 1 min read
 

 Article
Mumbai warned of ‘extremely heavy rain’ today, people advised to stay indoors

Mumbai rains: Met office has forecast ‘extremely heavy rain’ between Saturday and Monday in north coastal Maharashtra, including Mumbai. ...

Recently posted. 793 views . 1 min read
 

 Video
15 Things You Didn't Know About India



Recently posted . 682 views
 

 Reviews
Top 5 Bestseller Novels in India 2018



Recently posted . 3K views . 35 min read
 

 Reviews
Top 10 Real Estate Websites for Property Search



Recently posted . 1K views . 48 min read
 

 Article
Dowry Calculator: Leaders across parties slam website, owner says it's a satire

The website takes into account the details like groom’s age, caste, profession, salary, the university he attended, his skin colour and height to calculate ...

Recently posted. 821 views . 1 min read
 

 Article
Everything you need to know about Goods and Services Tax (GST)

GST is an Indirect Tax which has displaced many Indirect Taxes in India. The Goods and Service Tax Act were enacted in the Parliament on 29th March 2017. The Act ...

Recently posted. 859 views . 2 min read
 

 
 
 

   Prashnavali

  Thought of the Day

“प्रत्येक अच्छा कार्य पहले असम्भव नजर आता है।”
Anonymous

Be the first one to comment on this story

Close
Post Comment
Shibu Chandran
2 hours ago

Serving political interests in another person's illness is the lowest form of human value. A 70+ y old lady has cancer.

November 28, 2016 05:00 IST
Shibu Chandran
2 hours ago

Serving political interests in another person's illness is the lowest form of human value. A 70+ y old lady has cancer.

November 28, 2016 05:00 IST
Shibu Chandran
2 hours ago

Serving political interests in another person's illness is the lowest form of human value. A 70+ y old lady has cancer.

November 28, 2016 05:00 IST
Shibu Chandran
2 hours ago

Serving political interests in another person's illness is the lowest form of human value. A 70+ y old lady has cancer.

November 28, 2016 05:00 IST


ads
Back To Top